Report

This section is available only for editions higher than PQFORCE Smart

The report view of a project shows the last valid project report according to the report period. Previous reports can be accessed from the Navigator by navigating within the project.

What is a project report?

A Status Report documents the state of a project over a defined reporting period. Project health is measured across multiple dimensions called Project Indicators.

The report author can describe events that occurred during the reporting period and comment on the development of individual indicators, giving stakeholders an efficient overview of the current project status.

Reports can have two statuses: Reporting, where the report can be edited, and Closed, where the report is available for consultation only and can no longer be modified.

Workspace

1 STATUS REPORT

This section contains the identification details of the report for the active project.

  • Image: The image serves as a visual identifier of the project report. An image can simply be dropped here via drag & drop. Alternatively, an image can be copied and then pasted here by clicking on the circle and then pressing the CTRL+V key combination.

  • Name: This is the name of the project report. It is used to distinguish the different project reports.

  • Description: The description is a rich text field and can be used to enter a detailed description for the project report.

  • Start and End: These two date fields determine the reporting period, the time period covered by the active project report.

2 DESCRIPTION

This section provides an overview of the Report view and its two main sections, Review and Outlook and Project Indicators, to support the reporting process.

3 REVIEW AND OUTLOOK

This section contains two text fields for comments:

  • Report of this Reporting Period: summary of the most important remarks on the current reporting period.

  • Outlook for the Next Reporting Period: records comments and expectations for the upcoming reporting period.

4 PROJECT INDICATORS

This section contains the indicators of the project expressed in the status report, organised into different dimensions (End of Project, Reported Effort, Quality, plus the parent dimension TOTAL).

Each dimension includes the following qualitative indicators:

  • Status: a traffic light indicator describing the state of the dimension on the end date of the project report. The available status values are Failed, In danger and Ok.

  • Trend: an arrow indicator representing the outlook for the next reporting period. The available trend values are Worsening, Stable and Improving.

  • A comment field is available in each dimension to further explain the choice of a specific indicator.

Quantitative indicators are available only if target Key Figures have been defined in the Evaluation tab of the project's Details view (either End of Project Target or Reported Effort Target).

Such indicators include Target, Actual, Remaining, Forecast, and Delta values for each applicable dimension, providing a numerical basis for assessing project performance against the defined targets.

Quantitative indicators are calculated automatically by the system, identified by a calculator icon next to the value. These values can be manually overridden, in which case the calculator icon is replaced by a pencil icon; in this case, the automatically calculated values are still shown on mouseover for transparency. Clicking on the pencil icon deletes the manually entered value and restores the automatically calculated one.

In editions higher than PQFORCE Professional, all indicators are highly configurable. It is also possible to have multiple report types.

The Refresh button updates the report data to reflect the latest changes in the system.

Options Area

The following section describes in detail which settings can be made in the Options Area.

  • STATUS

    Reports can either be in the Reporting status, where the report can be compiled and edited, or the Closed one, where the report is finalised and can no longer be modified.

  • VIEW

    Reports: Opens a secondary workspace presenting a table with all past reports and their respective details, such as name, description, status, dates, and project indicators.

  • ACTIONS
    Clicking on the Print icon, the current project report can be printed or saved as PDF.

  • STATUS
    Reports can be configured with a customisable number of statuses and associated permissions.

  • VIEW

    • Reports: Opens a secondary workspace presenting a table with all past reports and their respective details, such as name, description, status, dates, and project indicators.

    • Plan TODOs in Kanban Board: Opens a secondary workspace with a Kanban board that displays all TODOs planned for the current report, allowing users to view all available TODOs and assign new ones.

    • Plan TODOs in List View: Opens a secondary workspace with a list of all TODOs planned for the current report, allowing users to view all available TODOs and assign new ones.

      • Properties: Allows selection of the property columns displayed in the list view.

      • Relations: Allows selection of the relation columns displayed in the list view.

  • PRINT OPTIONS
    These check boxes can be used to determine what additional information is available on a printout of the selected project report.

    • Project: If this check box is activated, the identification features of the project are also added to a printout of the project report.

    • Risks: If this check box is activated, the risks of the project report are also added to a printout of the project report.

    • Requests: If this check box is activated, the requests of the project report are also added to a printout of the project report.

    • History: If this check box is activated, the history of the project report is also added to a printout of the project report.

  • ACTIONS
    Actions can be performed here for the active view.

    • Print: Here the current project report can be printed with the attachments selected under PRINT OPTIONS.

↑

Notification

Portal tour

A guided tour walks you through the page step by step, highlighting one control at a time and explaining what it does. You can stop at any point and pick up later.